DUSAHNBE, May 12, Asia-Plus — A meeting to discuss measures to speed up the construction of “Sangtuda-1” hydropower plant in Tajikistan was held in the site for the plant on May 12, according to information from the Ministry of Energy.  The source says the deputy head of Unified Energy Systems of Russia (RAO YeES) Vyacheslav […]

Nazarali Pirnazarov

DUSAHNBE, May 12, Asia-Plus — A meeting to discuss measures to speed up the construction of “Sangtuda-1” hydropower plant in Tajikistan was held in the site for the plant on May 12, according to information from the Ministry of Energy. 

The source says the deputy head of Unified Energy Systems of Russia (RAO YeES) Vyacheslav Voronin, senior representatives from the “Barqi Tojik” (Tajik electric system) opened joint-stock holding company and companies working on the construction of the station by contract attended the meeting.  

The meeting summed up the results of work carried out on the construction of Sangtuda-1 station since the beginning of this year.  During the meeting it was noted that some contractor companies were behind the schedule at least by two months.  To date, almost 40 percent of a total volume of works have been reached, according to the source.   

Under protocol signed in Dushanbe in January last year Russia is completing the construction of Tajikistan’s Sangtuda-1 hydroelectric power on the Vakhsh River, some 120 kilometers east of Dushanbe.  The construction of the Sangtuda-1 station officially commenced on April 15, 2005.  The 670MWt Sangtuda-1 station will be capable to generate 2.7 billion kWh of electricity a year.  The estimated budget for the implementation of this project is US$482 million, and ownership shares are assessed as follows: RAO YeES owns 75 percent and Tajikistan – 25 percent.  

The station should be finished in four years, by April 15 2009.

Article translations:

Related Article

Оби зулол

Most Read

Join us on social media!

Aura

Recent Articles

Gasoline and diesel fuel in Dushanbe rose in price by 8.9% due to the war in the Middle East

The rise in global oil prices and, consequently, the cost of petroleum products has triggered the closure of the Strait of Hormuz.

The Ministry of Labor organizes consultations for migrants returning from Russia at Dushanbe airport

Employees of the Migration Service explain the requirements of Russian legislation and offer job vacancies in their homeland.

Tajikistan and Uzbekistan discuss simplification of customs procedures and implementation of VIN.TJ system

The VIN.TJ system is designed to simplify the process of vehicle registration and control.

Tajikistan climbs four places in the global fixed internet speed ranking

This is the country's best performance in the past five years.

President of Tajikistan launches hydro unit No. 7 at Nurek HPP

As of today, three units have been completely replaced at the country's largest hydroelectric power station.

Italian Opera in Dushanbe: Shohrukh Yunusov invites to an evening of musical revelations

The evening will feature the most recognizable Italian works alongside world and Tajik classics.

The European Union lifts sanctions on Tajik banks

This is attributed to successful reforms and improved financial transparency in the country.

Meta announced plans to lay off about 10% of its staff

The reason cited is the high costs of artificial intelligence development.

In Tajikistan, transplantation of two organs from a living donor successfully performed for the second time

Such operations are most often conducted in developed countries from deceased donors.