Electricity supplies the city of Kulob and Danghara increases by two hours

KULOB, January 12, 2009, Asia-Plus  — Electricity supplies to residential customers in the city of Kulob and the settlement of Danghara, the administrative center of the Danghara district have increased by two hours. Speaking in an interview with Asia-Plus, Ahmad Kishvarzov (phonetically spelled), engineer-in-chief at the Kulob city electric systems, said that electricity supplies to […]

Turko Dikayev

KULOB, January 12, 2009, Asia-Plus  — Electricity supplies to residential customers in the city of Kulob and the settlement of Danghara, the administrative center of the Danghara district have increased by two hours.

Speaking in an interview with Asia-Plus, Ahmad Kishvarzov (phonetically spelled), engineer-in-chief at the Kulob city electric systems, said that electricity supplies to the city of Kulob and the settlement of Danghara increased by two hours today.  Residential customers here now receive electricity supplies six hour per day: three hours of electricity in the morning and three hours in the evening.  Residents of other districts of Khatlon’s Kulob region still have four hours of electricity per day.

As it had been reported earlier, electricity rationing introduced in the city of Kulob on January 9 resulted in the supply of daily electricity to residential customers being reduced to four hours: two hours electricity in the morning (from 6:00 am to 8:00 am) and two hours in the evening (from 4:00 pm to 6:00 pm).

According to the Kulob city electric systems, the move stemmed from a decrease in the volume of electricity supplies from the hydroelectric power plant (HPP) Sangtuda-1.

Before January 9, Kulob had received electricity supplies from the Sangtuda-1 station at the rate of 60,000 kWh per day, while at present the city receives 33,000 kWh of electrical power from Sangtuda-1 per day

According to Kishvarzov, the Sangtuda-1 HPP currently generates 300,000 kWh of electricity; major part of it is supplied via substations Lolazor and Regar to the Tajik aluminum smelter in Turusnzoda as well as via the substation Guzar to the districts subordinate to the center. 

Article translations:

Related Articles

Оби зулол

Most Read

Join us on social media!

Recent Articles

Hajj 2026: New Rules and Restrictions Introduced in Saudi Arabia

Entry to Mecca is now only possible with a special permit.

Emomali Rahmon flies to Astana for the Regional Ecological Summit

President of Tajikistan Emomali Rahmon departed today for a...

Nexign and TelecomDaily: the telecommunications market in Tajikistan grew by 13.7% in 2025

A study showed that the country's communications market has grown to 4.9 billion somoni, and the dynamics are influenced by an increase in the subscriber base, growth in internet traffic, and expansion of mobile and fixed network coverage.

Tajikistan’s Parliament approves organized recruitment of migrants to Russia

The paperwork will be transferred to the home country, and employers will select employees in advance.

Creativity as an asset: why marketing in Central Asia is reaching a new level

Business expert in international projects for the support and development of media companies, Svetlana Lebedeva, on marketing and the media market.

European Immunization Week starts in Tajikistan

Information and awareness-raising activities are being conducted across the country to increase trust in vaccination and combat misinformation.

The plan to launch the CASA-1000 project in 2027 discussed in Dushanbe

The Ministry of Energy of Tajikistan, Afghan DABS, and other project participants held a series of meetings.