Construction of power grid from Sangtuda-1 HPP to Afghan border to be completed in September

DUSHANBE, August 2, 2010, Asia-Plus  — Construction of a power transmission line from the Sangtuda-1 hydroelectric power plant (HPP) to the Afghan border is expected to be completed in early September this year, according to Barqi Tojik power holding  (Tajik electricity supplier). The source at Barqi Tojik told Asia-Plus Monday afternoon that under the schedule […]

Payrav Chorshanbiyev

DUSHANBE, August 2, 2010, Asia-Plus  — Construction of a power transmission line from the Sangtuda-1 hydroelectric power plant (HPP) to the Afghan border is expected to be completed in early September this year, according to Barqi Tojik power holding  (Tajik electricity supplier).

The source at Barqi Tojik told Asia-Plus Monday afternoon that under the schedule the construction of a Tajik part of the Sangtuda-Puli Khumri power transmission line (the Tajikistan-Afghanistan 220 kV interconnection project) must be completed by Tajikistan’s Independence Day, which is marked on September 9.

We will recall that the Tajik side was expected to complete its part of the Tajikistan-Afghanistan 220 kV interconnection project in May this year but because of the rail problems (freight cars loaded with building materials for the power grid were being held up in Uzbekistan) the completion of the construction of the power transmission line on Tajik territory was delayed.

“The rail problems have been solved and freight cars carrying our cargo have arrived in Tajikistan.  All 416 pylons have already been installed on Tajik territory,” said the source, “In Afghanistan, the construction work is still being carried out at the Kunduz substation and they have installed 20 pylons and laid foundations of 110 other pylons to this day.  According to information we received from Afghanistan’s Ministry of Energy and Water, the construction of power transmission line on Afghan territory will be completed at the end of this year.”

A total cost of the Tajikistan-Afghanistan 220 kV interconnection project is 56.5 million U.S. dollars and it is financed by the Asian Development Bank (ADB), the OPEC Fund for International Development (OFID), the Islamic Development Bank (IsDB), the Afghanistan Reconstruction Trust Fund, and the governments of Tajikistan and Afghanistan.

On the territory of Tajikistan, the line starts in the Sanguda-1 hydroelectric plant and ends on the Tajik-Afghan border.  The 220 kV Tajikistan-Afghanistan power transition line is 280 kilometers long, and 118 kilometers of it lies on Tajik territory and 162 kilometers on Afghan territory. 

Article translations:
Оби зулол

Most Read

Join us on social media!

Aura

Recent Articles

Why Central Asia Needs Chinese Buses: A Report from the Yutong Factory

Today, Yutong is one of the main players in the market, having already delivered thousands of buses to the region: with adaptation to local conditions, service, and digital monitoring.

Emomali Rahmon shakes up officials

SCNS, MFA, State Television and Radio, and other structures

Tajikistan attracted €10 million for the modernization of the oncology center in Dushanbe

The Republican Oncology Research Center will be equipped with European equipment.

The export of Tajik electricity via the CASA-1000 line expected to begin next summer

This is promised by representatives of the company, the contractor for the Afghan section of this interregional power line.

ADB allocated $29.3 billion in 2025 to strengthen resilience in Asia and the Pacific

The bank allocated $8.3 billion for projects in Central and Western Asia.

Cotton planting starts in Tajikistan: farmers required to sow 70% of land

The Ministry of Agriculture says that no one has the right to force dehkans, but local authorities are exerting increasing pressure.

Against the backdrop of bombings of Iran, Tajik-Iranian bilateral trade decreased by almost 10%

The reduction in exports amidst the growth in imports has exacerbated the trade imbalance between Tajikistan and Iran.